Immission control - Submit measurement report on individual measurements of air pollutants at plants for the incineration and co-incineration of waste in accordance with 17. BImSchV
If you are the operator of a waste incineration or waste co-incineration plant, you must have the air pollutant emissions determined at regular intervals by means of individual measurements. The measurements must be carried out by a notified body (measuring centre) in accordance with Section 29b of the Federal Immission Control Act (BImSchG). You must draw up a measurement report on the results and submit it to the immission control authority responsible for you.
Forms/Online Services
Responsible authority
In most cases, the competent authority for installations that fall under the 17th BImSchV is Department 5, Environment, of the locally responsible regional council. In individual cases, a different responsibility may exist.
According to the Immission Control Competence Ordinance of the State of Baden-Württemberg (ImSchZuVO), the following applies:
The Departments 5, Environment of the respective locally responsible regional councils are the responsible immission control authorities for company premises on which
- at least one installation that is labelled with the letter E in column d of Annex 1 of the Ordinance on Installations Requiring a Permit,
- at least one operating area in accordance with Section 3 (5a) of the Federal Immission Control Act (hazardous incident operation),
- at least one installation which pursuant to § 60 para. 3 sentence 1 no. 2 or no. 3 of the Federal Water Act, or
- at least one landfill in accordance with Article 10 in conjunction with Annex I of Directive 2010/75/EU of the European Parliament and of the Council of 24 November 2010 on industrial emissions (integrated pollution prevention and control), as amended
exists or is to be constructed.
Department 9, State Office for Geology, Raw Materials and Mining of the Freiburg Regional Council is also the state-wide competent immission control authority for
- Operational sites, including the facilities and activities located on them, which are subject to mining supervision,
- Operating sites with cable cars and funicular railways used for passenger transport,
- Sites with high-pressure gas pipelines which, as energy installations within the meaning of the Energy Industry Act, serve to supply gas and which are designed for a maximum permissible operating pressure of more than 16 bar,
- Underground waste disposal facilities and
- Operating sites with facilities that serve the construction, significant expansion and significant modification of underground cavities.
The locally competent lower immission control authority (district or city administration) is the competent authority for all other industrial sites that do not fall under the regulations described above.
Details
Prerequisite
You are the operator of a plant for the incineration or co-incineration of waste in accordance with the Ordinance on the Incineration and Co-incineration of Waste (17th BImSchV).
Procedure
- You contact a notified body (measuring centre) in accordance with § 29b BImSchG.
- The exact measurement planning (measurement date, air pollutants to be measured, operating conditions of the installation to be taken into account) must be agreed between you, the measuring centre and the responsible immission control authority.
- The measuring centre determines the emission values on the measurement date.
- Once the measurement has been completed, you will receive a measurement report from the measuring centre which must be submitted to the responsible pollution control authority.
Deadlines
- If your system has been newly installed or significantly modified, you must have the measurements carried out every 2 months in the first year after commissioning and then regularly every 6 months thereafter.
- The measurement report must be submitted to the responsible authority no later than 8 weeks after the measurements.
Required documents
Complete measurement report in accordance with Annex A of Guideline VDI 4220 Sheet 2 (November 2018 edition) with information on, among other things
- Measurement results,
- measurement methods used,
- Operating conditions that are important for the assessment of the measurement results.
Costs
None
Miscellaneous
Please ensure that you submit the measurement report to the immission control authority responsible for your installation.
Legal basis
Gesetz zum Schutz vor schädlichen Umwelteinwirkungen durch Luftverunreinigungen, Geräusche, Erschütterungen und ähnliche Vorgänge (Bundes-Immissionsschutzgesetz -BImSchG):
- § 26 Messungen aus besonderem Anlass
- § 28 Erstmalige und wiederkehrende Messungen bei genehmigungsbedürftigen Anlagen
Siebzehnte Verordnung zur Durchführung des Bundes-Immissionschutzgesetz (Verordnung über die Verbrennung und die Mitverbrennung von Abfällen - 17. BImSchV):
- § 18 Periodische Messungen
- § 19 Berichte und Beurteilung von periodischen Messungen
Release note
Machine generated, based on the German release by: Umweltministerium Baden-Württemberg, 16.01.2026